Turnkey Renovation in Tashkent: Cost, Stages and Timeline in 2026

SAYF Studio · · Reading time: 9 minutes

The wall is still open. Cables run along the chases, and the pipes have already passed their pressure test. Before the plasterers close it up, the site manager photographs the whole wall. Five years from now, when you want to hang a shelf, that photo will tell you where not to drill. Turnkey renovation is made of details like this. Below: what it costs in Tashkent, how it runs week by week, and where clients most often lose money.

Turnkey renovation at SAYF

  • $600–4,000 per m²turnkey, furniture and appliances included, around $1,200 on average
  • 4–6 monthsan apartment of about 100 m², furniture included
  • 50 · 40 · 10three payments, each one after you’ve seen the result
  • 1 yearwarranty on all our work

How much does turnkey renovation cost in Tashkent?

With us, a square metre of turnkey renovation costs $600 to $4,000, covering labour, materials, furniture and appliances. The average is around $1,200, but treat it as a guide rather than a price: some clients order the renovation without appliances, and the average assumes budget-friendly ones. Premium appliances push the figure up just as natural stone does instead of tile. Our company fee is separate: 20% of the total renovation spend. For that, we run the whole job — the team, purchasing, supervision and the warranty.

It’s a wide range, and an honest one. Two 100 m² apartments built to the very same design can come out at completely different prices, because the design sets the shape and the materials set the price. Ceramic tile or natural stone on the bathroom floor. Laminate or parquet in the bedrooms. Painted walls or decorative plaster. A flat ceiling or one with recesses and lines of light. Each of these choices moves the estimate more than an extra ten square metres would.

That’s why we price every project individually. The estimate is built from the design project and working drawings, and you see it before you sign anything.

SAYF design projects
Modern Grace — 95 m² apartment, design project
Modern Grace — 95 m² apartment, design project
Warm Balance — 112 m² apartment, design project
Warm Balance — 112 m² apartment, design project

What “turnkey” means at SAYF

Design first, construction second. We don’t work any other way: starting a build without a design means gambling with your time, your money and the result.Sardor Sayfuddinov, founder of SAYF

We run the whole job: building services, finishes, furniture and fit-out. On site there’s a site manager and a technical supervisor; a procurement specialist handles purchasing, a project manager keeps you in the loop, and the designer makes sure the result matches the drawings. A construction director oversees them all. If something goes wrong, you know exactly who answers for it. Five tradesmen pointing at each other is not how we work.

By the time work starts, you already have a design project with working drawings and an estimate. No design yet? We’ll do it: what a design project costs.

Renovation timeline, week by week

An apartment of about 100 m², furniture included, takes four to six months. The exact figure depends on how complex the design is, the materials, and how quickly the furniture arrives. The baseline looks like this:

StageDuration
01 Contract and startweek 1
02 Strip-out and preparation1–2 weeks
03 Building services3–4 weeks
04 Rough finishing3–4 weeks
Furniture at the factoryin parallel with finishing
05 Final finishing4–5 weeks
06 Furniture and fit-out2–3 weeks
07 Cleaning and handoverweek 18

A week-by-week schedule for your project is attached to the contract. Only three things can push the date back: a late payment, a long wait for your choice of materials, or new work you decide to add.

The seven stages of a turnkey renovation

Everything that disappears into the walls gets checked twice before we close it up.SAYF Studio

01. Contract and start (week 1). The contract fixes the price from the preliminary estimate, the timeline, the payment schedule and the warranty. You get access to the online estimate, and we immediately order anything with a long lead time. From you we need the first payment, the keys and sign-off from the building management company. The crew is on site a few days after payment.

02. Strip-out and preparation (1–2 weeks). We take the space back to the shell, protect what stays and clear the debris. Then we measure everything again against the drawings: real walls rarely match the plan to the centimetre. The only thing we need from you is a decision if hidden defects turn up behind the old finishes.

03. Building services (3–4 weeks). The stage that matters most, because everything done here ends up hidden in the walls, floor and ceiling. Wiring and low-voltage networks, water, drainage, heating, ventilation and air-conditioning runs. We pressure-test the pipes, test every line and check it all twice before closing up. Every wall is photographed. You confirm the plumbing and appliance models and sign off the hidden work on a walkthrough.

04. Rough finishing (3–4 weeks). This is where the geometry appears: partitions and boxing-in, plaster laid to guide beads, floor screed, waterproofing in wet areas. Surfaces are checked with a level, and deviations have to stay within tolerance. You make your final choice of tile and flooring and approve the furniture drawings. From that day, the furniture goes into production.

05. Final finishing (4–5 weeks). The point where a project becomes an interior. Tile and porcelain stoneware, floors, ceilings with lines of light, the final coat of paint. Each material has its own specialist, and the designer comes by to check the work against the drawings. Your job is to approve the colour from a test patch on the wall and the tile layout.

06. Furniture and fit-out (2–3 weeks). The furniture arrives once the dust has settled and the finishes are done. We hang doors, install built-in wardrobes, put up the light fittings, connect plumbing and appliances and test every system.

07. Cleaning and handover (week 18). After a professional clean, we walk through every room with you. Any snags are fixed within an agreed time. You receive the warranty, appliance manuals and drawings of the hidden services — those wall photos. You have three working days to sign the handover certificate or list your remarks.

Payment: three instalments, no financing

We don’t offer financing. Payment comes in three parts, and each one is tied to work you can see with your own eyes. Amounts are based on the preliminary estimate attached to the contract.

  • 50% · startOn signing. This gets the work going and pays for long-lead materials.
  • 40% · midpointOnce strip-out, building services and floor preparation are done. We let you know, you walk the site, and only then do you pay.
  • ≈10% · handoverOn the handover certificate, at the actual cost of labour and materials. If you’ve paid more than the final figure, we refund the difference.

Any change or extra work is agreed with you in writing, in advance. You don’t pay for anything you didn’t approve.

How you keep track of the work and the money

You can open the online estimate on any day and see where the money has gone, in real time. There’s a camera on site, and photo reports come into a working Telegram group with the site manager, project manager and designer. A technical supervisor is on site every day. Hidden work is photographed before it’s closed up. Everything we build carries a one-year warranty.

15 mistakes that cost the most

Nearly all of them happen before the first tradesman walks through the door.

  1. Starting without a design project. Decisions get made on the fly, and then things get redone.
  2. Choosing a contractor on price alone. What you save at the start you usually pay back, with interest, at the end.
  3. Leaving no contingency. Keep 10–20% of the budget for the unexpected.
  4. Cutting corners on what goes inside the walls. Wiring, plumbing, ventilation and waterproofing matter more than expensive decorative finishes.
  5. Changing the design mid-renovation. Even a small change ripples through several stages.
  6. Placing sockets before the furniture layout is fixed. They end up behind the wardrobe, the sofa or the bed.
  7. Choosing materials on looks alone. How they age and how you clean them matters just as much.
  8. Underestimating lighting. Poorly planned light can make even an expensive interior look cheap.
  9. Leaving appliances and sanitaryware until later. Their dimensions are needed in the drawings.
  10. Copying a Pinterest picture as is. Your floor area, ceiling height and windows are different.
  11. Buying furniture before the design is approved. The designer then has to plan the room around the sofa.
  12. Hiring separate tradesmen with no one in charge. The work doesn’t join up, and nobody is to blame.
  13. Rushing the builders. Screed and plaster need time to cure, or cracks will follow.
  14. Skipping design and technical supervision. Mistakes surface when fixing them is already expensive.
  15. Designing for guests. You’re the one who lives there every day.
SAYF design projects
Olivea — 136 m² apartment, design project
Olivea — 136 m² apartment, design project
Quiet Elegance — 139 m² apartment, design project
Quiet Elegance — 139 m² apartment, design project

How to get a renovation estimate

Send us the floor area, the address (Tashkent or the region) and the design project, if you have one. We’ll come out, look at the space and prepare a preliminary estimate for your renovation specifically. More about our services: turnkey renovation, apartment design, house design.

You can tell a good renovation a few years on: the sockets are exactly where you need them, and there are no surprises behind the walls.

Frequently asked questions

How much does turnkey renovation cost per m² in Tashkent?

At SAYF, $600 to $4,000 per m² turnkey, covering labour, materials, furniture and appliances, around $1,200 on average. That’s a guide: the final figure depends on the materials and the appliances you choose. Our company fee is 20% of the total renovation spend. Every project is priced individually from the design.

Why do identical apartments cost different amounts?

Materials set the price: tile or natural stone, laminate or parquet. Two 100 m² apartments built to the same design can differ several times over in the estimate.

How long does a turnkey apartment renovation take?

An apartment of about 100 m², furniture included, takes 4–6 months. The timeline is written into the contract.

How is payment structured?

Three payments: 50% at the start, 40% at the midpoint after a site walkthrough, and about 10% on handover at the actual cost. We don’t offer financing.

What warranty do you give?

1 year on all work we carry out.

Do you renovate houses too?

Yes: apartments, private houses and commercial spaces in Tashkent and the Tashkent region.